Funds distribution and the execution lag

For the year's own appropriation: when the authority arrived and at what rate, when execution actually started and on what type of spending, how long each observable link took, and what a continuing resolution costs in execution days — measured from this Department's own six years rather than asserted.

Source
File A + File B + FPDS action dates + the curated appropriation calendar
Grain
Fiscal year x component x colour of money x object class major group
Vintage
2026-08-06
Rows loaded
6,574

Path accounts/file_a, accounts/file_b, contracts/, database/seed_approp_calendar.json · extracted 2026-09-19 04:54 · refresh With the warehouse; the calendar changes when a law is enacted

Limitations Apportionment, allocation, allotment and sub-allotment are published nowhere here, so only the endpoints of the chain are observed and the interior is an assumption with its authority printed beside it. The ramp is censored: only 1-6% of current-year dollars name their Treasury account, the attribution is award-level rather than action-level, and an earlier obligation that named no account is invisible. File A and File B hold one submission per fiscal year and contain no within-year series at all.

Own-year money only · FY2021–FY2026

Four bases, and which one every figure comes from

This page mixes measurement and assumption on purpose, because the question cannot be answered without both. What it must never do is let them blur, so each figure says which it is.

Measured · complete

File A and File B

Budget authority, resources, obligations, outlays, by object class. Every dollar — and one submission a fiscal year, so no within-year timing exists in them at all.

Measured · dated

The appropriation calendar

Enactment, continuing-resolution and lapse dates, each cited to its public law. Day-level.

Measured · censored

The execution ramp

Contract action dates against named accounts. An UPPER BOUND: 0.4% of FY2026 own-year obligations are visible this way, and the attribution is award-level.

Assumed

The interior of the chain

Apportionment, allocation, allotment and sub-allotment appear in no file available here. Only the endpoints are observed; the interior divides a measured residual.

Nothing assumed is ever added to anything measured. CHN-03 blocks a load where a unit assigns days to a step it never waited on, and CHN-01 ties every analytic unit back to File A’s own obligations for the year’s own money. The chain interior is the one part of this page that no control can verify, because there is nothing published to verify it against — which is itself the finding in section 5.

1 · One component, one colour of money, end to end

Authority, execution and the chain on the same day axis, because the whole point is that they line up. Day 1 is 1 October.

Enacted authority
$1047.16B
Total resources
$1151.09B
Obligated
$864.41B
75.1% of resources
Outlaid
$621.61B
71.9% of obligations
Unobligated
$286.68B

1 · When the money was there, and how much

Both ends are File A figures. Under a continuing resolution the account carries authority at the prior year’s annualised rate, which is the rule that shapes the middle; at enactment it carries its own enacted amount for the first time. Under a lapse it carries nothing.

OctNovDecJanFebMarAprMayJunJulAugSepAuthority$1047.16B maxP.L. 119-75 · day 126
  1. 2025-10-01 · d1lapse$0K[measured] No appropriation of any kind is in force. Obligation is barred except for excepted activities.
  2. 2025-11-12 · d43CR$140.03B[derived] The lapse ends and a continuing resolution takes effect. Authority is shown at the prior year's annualised rate, accrued from 1 October.
  3. 2026-01-31 · d123lapse$0K[measured] A second lapse. Authority already accrued remains obligated-against only for excepted activity; no new authority arrives.
  4. 2026-02-03 · d126enacted$1047.16B[measured] The full-year appropriation act is signed. The account carries its own enacted budget authority for the first time.

2 · When each type of spending actually moved

Each bar runs from the day a tenth of that object class’s observed obligation had been made to the day nine tenths had, with the median marked. Measured on contract actions that name this account, so it is an upper bound: an earlier obligation that named no account is invisible here. The first action is shown too, and it is deliberately not the measure — something obligates on 1 October in almost every year.

OctNovDecJanFebMarAprMayJunJulAugSepPrinting$0M · 9 actionsRent, comms and utilities$125M · 549 actionsTravel and transport$27M · 170 actionsSupplies and materials$117M · 733 actionsEquipment$382M · 254 actionsLand and structures$27M · 92 actionsContractual services$2.7B · 3,467 actions
○ first action observed● median daybar: 10% to 90% executed│ authority available┆ full-year act

3 · The chain, against the process that is supposed to run it

Two chains run in every one of these years, and which one governs a dollar depends on what the dollar is for. A continuing requirement has authority from 1 October at the prior year’s rate, OMB having apportioned automatically by bulletin, so only distribution and contracting remain. A new start is barred outright until the full-year act, and then the whole chain runs from the enactment date. The model below is built from the documented process and is never re-fitted to the observation; the verdict is how the two compare.

Continuing requirementmeasured from authority available (day 43)6 d observed against a model of 16–136 d (likely 60) — 10 days ahead of the fastest the chain could run
  1. measuredAppropriation in force—CongressThe full-year act is signed. Under a continuing resolution the account already holds authority at the prior year's annualised rate, so this step has already happened and the chain below starts from 1 October instead. Public law
  2. estimateFunding authorization document generated, staffed and signed3–21 dOUSD(C) appropriation manager, SES approvalThe FAD is drafted, staffed and signed, then issued to the Military Service or Defense Agency. This is the step that turns an apportionment into authority a component can actually distribute, and it has no published clock. DoD FMR Volume 3, Chapter 2
  3. regulationAllotment to the major command5–30 dComponent comptroller → major commandThe regulation is explicit here and nowhere else in the interior: allotments shall be made no later than 30 days after OMB signs the apportionment, or the start of the subsequent calendar month, whichever is later. Note the clock runs from OMB's signature, so it OVERLAPS the recording and FAD steps above rather than following them. DoD FMR Volume 3, Chapter 2
  4. estimateSub-allotment to the installation or fund centre3–25 dMajor command → fund centreThe command sub-allots to the organisation that holds the requirement. Nothing published records when this happens, for any component, in any year. DoD FMR Volume 3, Chapter 2
  5. estimateCommitment and solicitation5–60 dFund centre → contracting activityThe fund centre commits the funds and the contracting activity solicits. On an existing vehicle this is short; where competition is required it is the longest step in the chain and it is acquisition lead time rather than funds distribution. DoD FMR Volume 3, Chapter 15; FAR Part 6
  6. measuredFirst obligation recorded—Contracting activityA contract action is signed and the obligation is recorded. The second measured endpoint. FPDS action date
  7. The component request, OUSD(C) review, OMB apportionment and recording steps are not shown for this chain: under a continuing resolution OMB apportions automatically by bulletin, so they do not run at all.

Statute allows OMB 30 days from enactment to apportion and the regulation allows 30 more to allot, so 60 days from enactment to allotment is the ceiling law and regulation together permit. It is the one figure in this section that comes from neither estimate nor observation.

New start, after the actmeasured from full-year act signed (day 126)17 d observed against a model of 27–200 d (likely 89) — 10 days ahead of the fastest the chain could run
  1. measuredAppropriation in force—CongressThe full-year act is signed. Under a continuing resolution the account already holds authority at the prior year's annualised rate, so this step has already happened and the chain below starts from 1 October instead. Public law
  2. statuteComponent submits its apportionment request3–15 dMilitary Department or Defense Agency → OUSD(C)The component builds and submits its SF 132. Statute allows the agency until 15 days after enactment and A-11 asks for 10 calendar days; the component's own internal staffing sits inside that window. 31 U.S.C. 1513(b)(1); OMB Circular A-11 §120.23
  3. estimateOUSD(C) reviews and forwards to OMB2–12 dOUSD(C)/P&FC → OMBOUSD(C) consolidates the Department's requests, reconciles them against the enacted act and forwards the SF 132 to OMB. No published deadline governs this step, and it is one of the two places a Department-side delay would sit. DoD FMR Volume 3, Chapter 2
  4. statuteOMB apportions — SF 132 signed5–30 dOMBOMB must notify the agency of its apportionment action within 30 days of enactment. It is a manual, document-by-document action. Under a continuing resolution OMB apportions automatically by bulletin (A-11 §123), which is why operating accounts obligate from the first day of a CR year. 31 U.S.C. 1513(b)(1)
  5. estimateOUSD(C) records the approved apportionment1–7 dOUSD(C)/P&FCThe approved position is recorded in the Department's funds control system. Nothing can be distributed against an apportionment that has not been posted. DoD FMR Volume 3, Chapter 2
  6. estimateFunding authorization document generated, staffed and signed3–21 dOUSD(C) appropriation manager, SES approvalThe FAD is drafted, staffed and signed, then issued to the Military Service or Defense Agency. This is the step that turns an apportionment into authority a component can actually distribute, and it has no published clock. DoD FMR Volume 3, Chapter 2
  7. regulationAllotment to the major command5–30 dComponent comptroller → major commandThe regulation is explicit here and nowhere else in the interior: allotments shall be made no later than 30 days after OMB signs the apportionment, or the start of the subsequent calendar month, whichever is later. Note the clock runs from OMB's signature, so it OVERLAPS the recording and FAD steps above rather than following them. DoD FMR Volume 3, Chapter 2
  8. estimateSub-allotment to the installation or fund centre3–25 dMajor command → fund centreThe command sub-allots to the organisation that holds the requirement. Nothing published records when this happens, for any component, in any year. DoD FMR Volume 3, Chapter 2
  9. estimateCommitment and solicitation5–60 dFund centre → contracting activityThe fund centre commits the funds and the contracting activity solicits. On an existing vehicle this is short; where competition is required it is the longest step in the chain and it is acquisition lead time rather than funds distribution. DoD FMR Volume 3, Chapter 15; FAR Part 6
  10. measuredFirst obligation recorded—Contracting activityA contract action is signed and the obligation is recorded. The second measured endpoint. FPDS action date

Statute allows OMB 30 days from enactment to apportion and the regulation allows 30 more to allot, so 60 days from enactment to allotment is the ceiling law and regulation together permit. It is the one figure in this section that comes from neither estimate nor observation.

4 · Every dollar, by type of execution

File B, direct obligations, this unit’s own-year money. Complete — and carrying no timing at all, which is why it sits beside the censored ramp above rather than inside it.

Type of executionObligatedOutlaidUndeliveredOutlay rate
Pay and benefits$408.13B$400.66B$3.31B98%
Contractual services$238.23B$111.22B$121.35B47%
Equipment$101.43B$41.71B$58.51B41%
Supplies and materials$43.84B$29.40B$15.54B67%
Travel and transport$18.11B$10.52B$6.02B58%
Rent, comms and utilities$15.51B$8.47B$6.62B55%
Land and structures$7.42B$630M$6.73B8%
Grants and claims$2.42B$1.06B$1.26B44%
Undistributed$1.56B$1.60B$63M103%
Printing$535M$247M$276M46%
Investments and loans$60K$50K$10K83%
Other$-368K$95M$-6K-25861%

2 · What a continuing resolution actually costs in execution days

Each component and colour of money regressed against the number of days its year ran without a full-year act. Theil-Sen rather than least squares: with five or six observations one unusual year sets an ordinary slope, and two of these six years are unusual. Every year is compared over the same window — the shortest any year of that unit reaches — so a live year measured over fewer days does not read as running early.

Where the effect is
3 of 22
Component and colour-of-money pairs that slip more than 5 days per 30 days of continuing resolution: Navy family housing, Navy military construction, Army family housing. Construction and housing, and nothing else.
Everywhere else
-1.6 / -0.2 days
Median slope for operating and for investment accounts. Both are within two days of zero: for most of the Department the length of the continuing resolution does not move execution timing at a level this data can detect.
Evidence depth
4 years
The three exposed pairs rest on four observations each, which is the minimum this page will publish a slope on. Treat the direction as established and the magnitude as provisional.

The Department and its components, all colours of money together

ScopeWindowYearsDays later per 30 days of CR
Department of War (all components)218 d6-3.4
Air Force — all colours of money218 d6+0.4
Navy — all colours of money213 d6-1.0
Army — all colours of money217 d6-2.7
Defense-wide — all colours of money218 d6-4.0

Rolled up, the effect disappears entirely: the Department as a whole and every component sit within a few days of zero. That is not the same as saying nothing is affected — it is the arithmetic of a small number of exposed accounts inside a very large total, which is exactly why the table below is the one to act on.

Component by colour of money

ComponentColour of moneyProfileWindowYearsDays later per 30 days of CR
NavyFamily housinginvestment345 d4+27.1
NavyMilitary constructioninvestment363 d4+13.6
ArmyFamily housinginvestment113 d4+12.5
ArmyMilitary personneloperating209 d6+3.3
ArmyProcurementinvestment64 d6+3.1
Air ForceOperation and maintenanceoperating218 d6+2.8
ArmyMilitary constructioninvestment79 d6+1.5
Defense-wideDefense Health Programoperating217 d6+1.3
NavyRDT&Einvestment361 d5+1.2
Air ForceRDT&Einvestment204 d6+0.1
Defense-wideOperation and maintenanceoperating218 d6-0.4
Air ForceFamily housinginvestment114 d5-0.5
Defense-wideProcurementinvestment211 d6-1.3
ArmyRDT&Einvestment365 d5-1.3
Air ForceProcurementinvestment198 d6-1.8
ArmyOperation and maintenanceoperating217 d6-2.9
NavyOperation and maintenanceoperating213 d6-3.9
NavyProcurementinvestment72 d6-4.4
Defense-wideRDT&Einvestment211 d6-5.3
Defense-wideOtheroperating351 d5-7.8
Air ForceMilitary personneloperating184 d6-11.4
Air ForceMilitary constructioninvestment350 d5-30.2

A positive figure means execution slipped later as the continuing resolution ran longer. A negative one means it did not, and several are negative: an account whose requirements already exist obligates at the prior year's rate whether or not the new act has passed. CHN-05 re-derives every slope in SQL from the points it was taken over, sharing no code with the extract that published it.

The shape of this table is the finding, and it is not the one an execution review usually starts from. Both medians sit within two days of zero, so a continuing resolution has no effect on most of the Department that this data can detect. The effect lives entirely in the tail, and the tail is construction and family housing. The negative rows are not noise either: an account whose requirements already exist obligates at the prior year’s rate whether or not the new act has passed, and several of them obligate earlier in a long continuing resolution, which is what carrying a backlog into October looks like.

Two cautions on reading it. The three exposed pairs have four observations each, so the direction is better established than the magnitude. And Air Force military construction at the bottom of the table, at -30.2 days, is a single-account series whose sign is set by two years; it is published because deleting an inconvenient row is how a table stops being evidence, not because it is believed.

3 · Where the wait actually is

The measured gap between the day a unit first had authority and the day a tenth of its observed year had been obligated. Both ends are measured; nothing here is assumed.

The longest measured waits

FYUnitAuthority10% executedGap
2023Defense-wide · Military constructionday 1day 356355 d
2024Defense-wide · Military constructionday 1day 349348 d
2025Army · Military constructionday 1day 309308 d
2021Air Force · Military constructionday 1day 302301 d
2024Army · Family housingday 1day 287286 d
2023Army · Otherday 1day 265264 d
2025Army · Family housingday 1day 260259 d
2023Air Force · Procurementday 1day 257256 d
2022Navy · Family housingday 1day 253252 d
2022Defense-wide · Military constructionday 1day 250249 d
2025Air Force · Military constructionday 1day 247246 d
2021Defense-wide · Procurementday 1day 239238 d

Construction and family housing dominate, and that is the honest reading: their wait is design, solicitation and source selection, not a funds distribution delay. The chain profile in section 1 charges it accordingly.

Units that executed before the authority arrived

FYUnitAuthority10% executedAhead by
2026Air Force · Operation and maintenanceday 43day 1330 d
2026Air Force · Family housingday 43day 3112 d
2026Army · Military personnelday 43day 376 d
2025Air Force · Military personnelday 1day 10 d

Almost all of these are FY2026, where the year opened with a 43-day lapse and operating accounts kept obligating anyway — on excepted activity and on carried-in balances. It is the clearest evidence on the page that operating execution is not gated by the new appropriation.

4 · After the act: how long until the money that had to wait actually moved

The new-start chain. Obligation that could only follow the full-year act, measured from the day it was signed, against the process model built from statute, regulation and the steps nobody publishes a clock for.

FYComponentAct signedFirst tenth placedDays after the actAgainst the model
2023Air Forceday 90day 17484 dwithin the model
2023Armyday 90day 16676 dwithin the model
2022Armyday 166day 23670 dwithin the model
2023Defense-wideday 90day 16070 dwithin the model
2021Armyday 88day 14658 dwithin the model
2021Defense-wideday 88day 13951 dwithin the model
2023Navyday 90day 13949 dwithin the model
2021Air Forceday 88day 12840 dwithin the model
2022Navyday 166day 20135 dwithin the model
2024Armyday 175day 20934 dwithin the model
2021Navyday 88day 11729 dwithin the model
2026Navyday 126day 15428 dwithin the model
2026Defense-wideday 126day 15327 dwithin the model
2024Navyday 175day 20126 dahead by 1 d
2026Armyday 126day 14923 dahead by 4 d
2022Defense-wideday 166day 18822 dahead by 5 d
2024Defense-wideday 175day 19419 dahead by 8 d
2022Air Forceday 166day 18115 dahead by 12 d
2026Air Forceday 126day 14014 dahead by 13 d
2024Air Forceday 175day 1805 dahead by 22 d

The model's likely path — every step at its typical duration — totals 89 days. Most components beat it, and that is the finding: the work was staged and waiting on authority rather than starting when the authority arrived. 2 chains run beyond it.

Read the spread rather than the level. Both components are inside a model that runs from 27 to 200 days, which is wide enough that “within the model” is a weak statement on its own. The useful comparison is between components running the same statute in the same year, and there the difference is real and consistent.

5 · What the law puts between an appropriation and an obligation

Conditions in appropriations law and the joint explanatory statements. Two kinds, and conflating them is the commonest error in this area: a BAR prevents obligation until the condition is met; a reporting direction burdens the Department without, on its own words, withholding the money.

Gates that bar obligation
4 of 9
The rest direct a report or a spend plan. A reporting direction is a real burden and it is not the same thing as money that cannot be touched.
The one that governs everything
No new starts
A continuing resolution funds the prior year's activities at the prior year's rate and bars new starts, multi-year procurements and production-rate increases. It is the mechanism behind section 3.
Statutory ceiling to allotment
60 days
Thirty days for OMB to apportion after enactment (31 U.S.C. 1513(b)(1)) plus thirty for the component to allot after that signature (DoD FMR Volume 3). The only end-to-end figure on this page that comes from law alone.

What a gated account looks like in the execution data

The FY2026 agreement attaches a 60-day spend plan to Golden Dome. File A can isolate that account, so the scope is measured rather than asserted: it received $8.2B of budget authority and obligated $0.02B, 0.2%, in its year of appropriation, then $19.18B of $21.12B, 90.8%, in the year after. That is the shape a gated new fund makes. The direction and the slow year are not the same event \u2014 the money was appropriated before this act, and a first-year investment fund executes slowly for many reasons. What this shows is the pattern, not a cause.

bars obligationEvery appropriation, on enactment30 daysquoted

“The agency submits its apportionment request by the later of 40 days before the fiscal year begins or 15 days after enactment; the President notifies the agency of the apportionment action by the later of 20 days before the fiscal year begins or 30 days after enactment.”

Funds cannot be distributed before they are apportioned. Thirty days is the statutory ceiling on OMB, not a target, and it runs from enactment rather than from receipt of the request.

31 U.S.C. 1513(b)(1) \u00b7 source

bars obligationEvery account, while a continuing resolution is in forcedescribed

A continuing resolution funds projects and activities at the prior year's rate and bars new starts, multi-year procurements and production-rate increases. An activity for which no appropriation was available in the prior year cannot be obligated against at all until the full-year act.

This is the single most consequential gate on this site, and it is the mechanism behind the continuing-resolution finding in section 2: operating accounts keep obligating at the prior year's rate through a CR because their requirements already exist, and construction and family housing cannot, because a project that has not started is precisely what the CR bars.

Continuing Appropriations Act, 2026, §102 and §104 \u00b7 source

bars obligationAny movement of funds above the agreed thresholdsdescribed

The Department's Financial Management Regulation requires prior congressional approval of reprogramming actions above dollar or percentage thresholds agreed with the congressional defense committees. General transfer authority is separately capped by the act: $6,000,000,000 between appropriations for military functions other than military construction in the FY2024 act.

The specific thresholds by appropriation type are not published in the source this site could reach, so they are not stated here. The transfer ceiling is quoted for FY2024, the year the source states; it is set annually and this site has not verified the FY2026 figure.

DoD FMR Volume 3, Chapter 6; annual Department of Defense Appropriations Act, §8005 \u00b7 source

bars obligationUSAFRICOM area of operations, additional $25,000,000FY2026quoted

“The agreement directs that none of these funds may be obligated or expended until the Under Secretary of Defense (Comptroller), in coordination with the Commander, USAFRICOM, presents an execution plan to the congressional defense committees.”

The clearest example on this page of a true bar rather than a reporting direction: the money exists and cannot be touched until a document reaches the committees. It carries no deadline, so the wait is as long as the staffing takes.

Joint Explanatory Statement, Department of Defense Appropriations Act, 2026 \u00b7 source

reporting directionEvery appropriation, after apportionment30 daysquoted

“Allotments shall be made no later than 30 days after OMB signs the apportionment or the start of the subsequent calendar month, whichever is later.”

The only step in the interior of the distribution chain with a published deadline. Note the clock runs from OMB's signature, so it overlaps the recording and funding-authorization-document steps rather than following them: statute and regulation together allow 60 days from enactment to allotment.

DoD FMR Volume 3, Chapter 2 \u00b7 source

reporting directionEvery account, while a continuing resolution is in force0 daysdescribed

OMB apportions continuing-resolution funding automatically by bulletin, at a pro-rata share of the annualised prior-year rate: rate for operations multiplied by the days the continuing resolution covers, divided by 365.

This is why a continuing resolution does not stop operating execution. The apportionment steps of the chain do not run at all: the authority is already apportioned on 1 October. It is also the rule this site uses to draw the authority curve under a continuing resolution.

OMB Circular A-11 §123 \u00b7 source

reporting directionGolden Dome for America Fund, DefenseFY202660 daysquoted

“To that end, the Secretary of Defense is directed, in conjunction with the Director of Golden Dome, to provide a comprehensive spend plan for Golden Dome resourcing to the congressional defense committees, not later than 60 days after enactment of this Act.”

Measured scope: $8.2B budget authority, $29.3B resources, $19.2B obligated across FY2025, FY2026 \u2014 account 097-2025/2029-3007-000.

A direction to report rather than a bar on obligation in its own words. The account it names is the one large enough to see in File A, which is why this site can measure its scope instead of asserting it.

Joint Explanatory Statement, Department of Defense Appropriations Act, 2026 \u00b7 source

reporting directionJIATF-401 (counter-small-unmanned-aircraft-systems task force)FY202660 daysquoted

“Further, the agreement directs that not later than 60 days after the enactment of this Act, the Secretary of the Army shall submit a comprehensive spend plan for amounts made available for JIATF-401.”

Sits inside Army accounts rather than in one of its own, so File A cannot isolate its scope and this site does not guess at it.

Joint Explanatory Statement, Department of Defense Appropriations Act, 2026 \u00b7 source

reporting directionTaiwan Security Cooperation InitiativeFY202660 daysquoted

“The agreement directs the Secretary of Defense, in consultation with the Commander, United States Indo-Pacific Command, to provide the House and Senate Defense Appropriations Subcommittees, not later than 60 days after the enactment of this Act, with a spend plan and briefing on the Taiwan Security Cooperation Initiative.”

A reporting direction with a deadline rather than a bar.

Joint Explanatory Statement, Department of Defense Appropriations Act, 2026 \u00b7 source

This is a selection read out of the acts and statements, not a mechanical extraction of every congressional direction, and it says so. Reprogramming thresholds by appropriation type are not published in any source this site could reach, so no figure is given for them. Where a gate sits inside a component’s accounts rather than in one of its own, File A cannot isolate it and the scope is left empty rather than estimated \u2014 GATE-01 fails a load that claims a measured scope without naming the account it was measured on.

6 · What the shapes themselves say

Execution ramps clustered by their own shape rather than by a category assigned in advance, and each unit-year scored against its own history. Deterministic: the same load gives the same archetypes, and the centroid rides on every row so a reader can see what the cluster actually is.

Execution archetypes

Even through the year

84

unit-years

Half the year’s obligation placed by fiscal month 5.

Front-loaded

42

unit-years

Half the year’s obligation placed by fiscal month 3.

Back-loaded

35

unit-years

Half the year’s obligation placed by fiscal month 7.

Unit-years furthest from their own history

DeviationWhat movedSamplePrior median sampleYears
-11.2FY2026 Air Force operation and maintenance placed half its observed obligation on day 59 against a 5-year median of 134$0.7B$1.4B5
-7.5FY2024 Defense-wide procurement placed half its observed obligation on day 87 against a 3-year median of 139$0.4B$0.0B3
+7.4FY2024 Army military construction placed half its observed obligation on day 67 against a 3-year median of 34$0.1B$0.0B3
-7.3FY2026 Defense-wide defense health program placed half its observed obligation on day 72 against a 5-year median of 115$0.3B$0.4B5
-6.8FY2024 Air Force military construction placed half its observed obligation on day 201 against a 3-year median of 304$0.1B$0.1B3
-6.6FY2024 Air Force operation and maintenance placed half its observed obligation on day 90 against a 3-year median of 134$2.3B$1.4B3
-6.6FY2024 Air Force procurement placed half its observed obligation on day 53 against a 3-year median of 160$0.0B$0.0B3
-6.0FY2026 Army operation and maintenance placed half its observed obligation on day 73 against a 5-year median of 126$0.7B$1.0B5
-5.8FY2024 Defense-wide rdt&e placed half its observed obligation on day 110 against a 3-year median of 155$0.5B$0.1B3
-5.6FY2026 Air Force procurement placed half its observed obligation on day 69 against a 5-year median of 160$0.2B$0.0B5
+5.2FY2025 Air Force family housing placed half its observed obligation on day 108 against a 3-year median of 77$0.0B$0.0B3
-5.1FY2026 Army all colours placed half its observed obligation on day 72 against a 5-year median of 133$0.8B$2.3B5

Median and scaled median absolute deviation against the unit's own prior years, scale floored at 5% of the median and the result capped at 99 \u2014 never against a Department average, because these categories differ by three orders of magnitude. The two sample columns are the point: a cell whose dated sample collapsed shifts its own median for reasons that have nothing to do with execution, and several rows here are exactly that. CHN-09 re-derives every baseline in SQL.

7 · Root cause

Why the pattern looks the way it does, and what each explanation would predict that this data can check.

1

A continuing resolution bars new starts, and a construction project is all new start

What supports it
Every pair that slips more than 5 days per 30 days of CR is construction or family housing, and those same accounts dominate the measured-wait table. A project that cannot be started cannot be obligated against, and there is no continuing requirement underneath it to keep obligating in the meantime.
What cuts against it
It does not generalise to investment money as a class: the investment median is -0.2 days, statistically indistinguishable from the operating median of -1.6. Procurement and RDT&E, which also need new starts, do not show the effect.
What this data can say
Right for construction and housing, wrong as a statement about investment accounts generally. The distinction matters because it decides where mitigation goes.
2

Acquisition lead time sets the level; the appropriation sets the variance

What supports it
Design, solicitation and source selection for a construction project take the better part of a year regardless of when the money arrived. That produces exactly what is seen: a long baseline wait that shifts modestly with the calendar.
What cuts against it
If lead time were the whole level, the slope would be zero and it is not — Navy family housing and military construction both move materially with CR length.
What this data can say
The best available reading. Level is acquisition; variance is appropriation. They need different remedies and are currently managed as one problem.
3

The distribution chain itself is slow

What supports it
The classic explanation, and the one the Department's own workforce reports.
What cuts against it
Nothing here can test it. Apportionment, allocation, allotment and sub-allotment are published in no file available to this site, so the interior of every chain on this page is an assumption sitting inside a measured residual.
What this data can say
Untestable with public data. That is a finding about instrumentation, not a verdict on the chain.
4

The ramp is an artefact of which contracts name their account

What supports it
Only 0.4% of FY2026 own-year obligations are visible in the dated ramp, and the account is attributed at award level rather than action level.
What cuts against it
The pattern is stable across six years and reverses cleanly between operating and investment accounts. A coverage artefact would not produce a sign change that tracks the economics.
What this data can say
A real limit on precision, not on the direction. Every ramp figure is labelled an upper bound.

8 · Courses of action

Four, ordered by the ratio of what they would change to what they would cost. Each names the evidence it rests on and how you would know it worked.

COA 1

Aim continuing-resolution mitigation at construction and family housing

Do
Build the CR playbook — anomaly requests, new-start exception lists, pre-award authorisations — around the 3 pairs that actually move: Navy family housing, Navy military construction, Army family housing. Do not spend the request capital on operating accounts.
Because
Measured over six years, the median slope is -1.6 days for operating accounts and -0.2 for investment accounts — no detectable effect either way. Every pair above 5 days is construction or family housing. A Department-wide CR mitigation spends most of its effort on accounts that do not respond to it.
Know it worked
The slope on those three pairs. Re-run it each year; a mitigation that works pulls them toward the zero the rest of the Department already sits at.
COA 2

Instrument the distribution chain so the argument can be settled

Do
Capture and publish four dates per funds-distribution action — apportionment, allocation, allotment, sub-allotment — from the systems that already create them, into the same reporting stream that carries obligations.
Because
Six of the nine steps in section 1 have no published clock at all. Statute gives OMB 30 days to apportion and the regulation gives the component 30 more to allot — 60 days end to end — and nothing records whether either was met, for any component, in any year. The Department cannot currently demonstrate whether the wait between authority and execution is distribution or acquisition, which means it cannot tell whether any remediation worked.
Know it worked
The model in section 1 spans 27–200 days for the enacted chain because six of its steps are estimates. Four recorded dates per distribution action would collapse that range to a measurement, and the estimate rows would disappear from this page.
COA 3

Separate the acquisition-lead-time problem from the appropriation problem

Do
For construction and family housing, move design and solicitation ahead of appropriation where authority permits, so the award is ready when the money is. Track design-complete-to-award separately from authority-to-award.
Because
These accounts carry 200-350 day waits from authority to first tenth even in years enacted in December. That level is not a funding delay and will not respond to funding remedies.
Know it worked
Authority-to-first-tenth for those units should fall toward the solicitation cycle rather than track the calendar.
COA 4

Triage the legislative gates by whether they actually bar obligation

Do
Maintain a single register of the conditions that gate obligation, separating the 4 that bar it from the reporting directions that do not, and put a named owner and a due date against each bar. Section 5 is the starting inventory.
Because
A direction to submit a spend plan and a clause reading 'none of these funds may be obligated or expended until' are managed today as one category of congressional homework. Only the second stops money moving, and the USAFRICOM clause carries no deadline at all, so its wait is as long as the staffing takes.
Know it worked
Days from enactment to the condition being met, per bar. It is not currently measured anywhere.
COA 5

Fix account attribution on contract actions

Do
Require the funding Treasury account on the action, not only on the award, in contract writing systems feeding the public files.
Because
Execution timing is currently measurable on 0.4% of own-year obligations. Every timing figure on this page is an upper bound because of it, and no amount of analysis fixes a coverage problem.
Know it worked
Coverage. At 50% the ramp stops being an upper bound and becomes a measurement.

Nothing on this page observes impropriety and nothing on it establishes causation. A consistent association between the appropriation calendar and the shape of execution, measured over six years against each unit’s own history, is what these files support. The mechanism is what a programme office, a comptroller and a contracting activity would have to be asked — which is the point of course of action 2.

9 · What this page cannot do, stated plainly

So that the next person does not rediscover it.

  • There is no monthly File A or File B. The warehouse holds one submission per fiscal year and the files themselves carry one period: the “P01-P12” in a download’s filename is the request range, not its content. A true monthly obligation curve at full coverage would need each period requested separately, which is a fetch rather than a code change.
  • File C is quarterly here, not monthly. It carries eleven period labels but only four of them hold content, and it reaches a few per cent of contract dollars.
  • Commitments are not published at all. The step between a fund centre receiving money and an obligation being recorded is invisible in every file on this site.
  • The ramp cannot see payroll. Pay and benefits move on a schedule through no contract action, so the one type of execution with no timing question in it is also the one the dated sample barely contains. That is why the complete File B table sits beside the ramp rather than inside it.

The companion page, fund distribution and the execution timeline, takes the same calendar and reads it against all contract obligations by fund holder, where coverage is complete and the colour of money is not available. The two answer different halves of the same question.

The argument these pages add up to, with what follows from it for the Department, the components and the appropriations committees, is written up at Where the time goes.